Oakleaf worked approximately half a million man hours on this major project without one reportable incident to the Health and Safety Agency. At the time, this was Ireland’s single largest construction site. The project involved a 75,000m2 terminal building, incorporating passenger and baggage processing, security screening, over 9,000m2 of retail outlets and a new 25,000m2 pier. Terminal 2 opened in November 2010 as a critical element in Ireland’s national transport infrastructure being praised for its innovative design and quality of finish. Oakleaf proudly received the FPDC “Drylining commercial contracts over £1m” in UK & Ireland award for quality of works carried out on this project.
In addition to the main T2 contract & Pier E Oakleaf completed numerous fit-out contracts including:
Etihad Lounge
This executive lounge will welcome business & premier club class travelers arriving from the middle east.
Hanger 2 (Ryanair):
Included specialist details to incorporate client requirement for security and sound proofing.
Hanger 6 (Aerlingus):
Included a fast track programme and consists of partitions, drylining & suspended ceilings with some feature bulkheads.
Retail Units:
These included Jo Malone, Wrights of Howth, Airport Pharmacy & Hugo Boss
Project Details
Project:
Dublin Airport – Terminal 2
Main Contractor:
PJ HegartyLocation:
DublinContract Value:
€20m